There has been some significant progress on the exterior of the house over the last two days. Namely the stucco has color and we have a garage door!
Saturday, August 31, 2013
We have a garage door!
Notice the nice trim color around the windows, doors and arches.
They have also mostly finished mudding and taping the drywall.
Posted by Casey at 11:11 PM 1 comments
Thursday, August 29, 2013
Our House: 6 weeks to go!
The house is still coming along. Not so many noticeable things on the exterior, but more on the interior now. Though we do have the garage door installed!
They have been busy putting up the drywall and mudding and taping it. Here are a few pics from the last few days...
Standing in the garage looking into back and the door to the workroom.
The kids love dancing in all the empty space.
Looking into the dining room and great room from the stair landing.
Claire doing some more dancing.
An exterior shot. The stone work is done, just
waiting on the other stucco coats and the
rain gutters and the outside is done.
waiting on the other stucco coats and the
rain gutters and the outside is done.
Posted by Casey at 8:11 PM 0 comments
Friday, August 23, 2013
Our House Catching Up
We were gone to Tucson for 2 1/2 weeks so we missed out on a lot of the house progress, but here are some pictures to catch up on what is going on...
Framing going up
From the inside
Waiting for the roof trusses. The manufacturer
was several days late delivering them.
was several days late delivering them.
We have a roof and shingles!
This last one is from yesterday. They have finished the
first coat of stucco on the house and are now giving an
estimated completion date of Oct. 4 or 5, which is awesomely fast!
first coat of stucco on the house and are now giving an
estimated completion date of Oct. 4 or 5, which is awesomely fast!
Posted by Casey at 12:06 PM 1 comments